Water Pump Suppliers in UAE | Solar Water Heater Supplier in UAE | Booster Pump Suppliers in UAE | Pressure Vessel Suppliers in UAE | GRP Water Tank
  • Home
  • About Us
  • Products
    • Pumps >
      • Booster Pumps
      • Submersible Pumps
      • Horizontal Multistage
      • Circulation Pumps
      • Lowara Pump
      • Ebara Pump
    • Solar Water Heater >
      • Ariston Solar Water Heater
    • Pressure Vessel >
      • Wates Pressure Vessel
      • Aquasystem Pressure Vessel
  • Contact
  • Home
  • About Us
  • Products
    • Pumps >
      • Booster Pumps
      • Submersible Pumps
      • Horizontal Multistage
      • Circulation Pumps
      • Lowara Pump
      • Ebara Pump
    • Solar Water Heater >
      • Ariston Solar Water Heater
    • Pressure Vessel >
      • Wates Pressure Vessel
      • Aquasystem Pressure Vessel
  • Contact

Wates Pressure Vessel Blog

How to Commission and Test a Wates Pressure Vessel After Installation

12/28/2025

0 Comments

 
Wates Pressure Vessel Supplier in UAE
Correct commissioning and testing are the final and most critical steps after installing a Wates pressure vessel.
Even a perfectly installed vessel can fail to perform if commissioning is skipped or done incorrectly.
Proper testing ensures:
  • Stable system pressure
  • Correct pump operation
  • Reduced cycling and energy consumption
  • Long service life of the vessel and pump

2. When Commissioning Should Be Done
Commissioning must be carried out:
  • After mechanical installation is complete
  • Before the system is handed over to the client
  • After any bladder replacement or major maintenance
  • After pressure switch or VFD settings are changed
Never commission a pressure vessel while the system is partially installed or under construction.

3. Pre-Commissioning Safety Checks
Before pressurizing the system, verify the following:
  • Vessel is securely mounted (no load on pipework)
  • Correct orientation (vertical or horizontal as per model)
  • Isolation valve, drain valve, and pressure gauge installed
  • All fittings tightened and sealed correctly
  • Vessel pressure rating matches system maximum pressure
  • Installation area is safe, ventilated, and accessible

4. Step-by-Step Commissioning Procedure
Step 1: Isolate and Fully Drain the Vessel
  • Close the isolation valve between vessel and system
  • Open the drain valve to remove all water from the vessel
  • Ensure zero water pressure inside the tank
This step is essential—pre-charge must never be checked with water inside the vessel.

Step 2: Check and Set Pre-Charge Pressure
  • Use a reliable air pressure gauge on the Schrader valve
  • Compare reading with required value
Correct rule:
Pre-charge = Pump cut-in pressure − 0.2 to 0.5 bar
Example:
  • Pump cut-in: 2.5 bar
  • Vessel pre-charge: 2.0–2.3 bar
Adjust using an air pump or release air as required.
Re-fit the valve cap tightly (preferably metal).

Step 3: Open Isolation Valve and Refill System
  • Slowly open the isolation valve
  • Allow water to enter the vessel
  • Observe pressure gauge for smooth pressure rise
Check all joints and fittings for leaks.

Step 4: Start the Pump and Observe Cut-Out Pressure
  • Start the pump and allow system to reach cut-out pressure
  • Confirm cut-out pressure is below vessel maximum rating
  • Ensure pump stops cleanly without pressure overshoot

Step 5: Test Drawdown Performance
  • Open a tap or outlet downstream
  • Observe pressure drop on gauge
  • Confirm water flows from the vessel before pump restarts
This confirms the vessel is storing usable water volume correctly.

Step 6: Verify Pump Cycling Frequency
  • Run system under normal demand conditions
  • Confirm pump does not short-cycle
  • Typical acceptable range: 10–20 starts per hour
Excessive cycling indicates incorrect pre-charge or undersized vessel.

5. System Stability Tests
5.1 Pressure Stability
  • Pressure should drop gradually, not suddenly
  • No pressure hunting or oscillation
5.2 Noise and Vibration
  • No banging, knocking, or water hammer
  • Vessel should remain stable without movement
5.3 Multi-Pump or VFD Systems
  • Pumps should sequence smoothly
  • No rapid on/off switching
  • Pressure sensor readings should remain steady

6. Final Inspection Checklist
Before handover, confirm:
  • Pre-charge pressure recorded
  • No air or water leaks
  • Isolation valve operational
  • Drain valve accessible
  • Pressure gauge readable and accurate
  • Vessel fully supported and aligned
  • System pressure within design limits

7. Common Commissioning Mistakes to Avoid
  • Checking pre-charge with water inside the vessel
  • Skipping drawdown test
  • Ignoring pump cycling frequency
  • Leaving isolation valve partially closed
  • Failing to tighten Schrader valve cap
  • Not documenting final pressure settings

8. Documentation and Handover
Record the following for future maintenance:
  • Vessel model and capacity
  • Pre-charge pressure value
  • Pump cut-in and cut-out settings
  • Commissioning date
  • Installer or technician name
This documentation is essential for warranty and service history.

9. UAE / GCC Commissioning Notes
  • High ambient temperature may slightly increase pressure after commissioning
  • Re-check pre-charge after 24–48 hours of operation
  • In hot pump rooms, schedule pre-charge inspection every 3–6 months
  • Coastal installations require periodic inspection for corrosion
Commissioning and testing are not optional steps—they determine how well a Wates pressure vessel will perform throughout its service life.
Correct pre-charge adjustment, drawdown testing, and pump cycling verification ensure:
  • Stable pressure
  • Reduced energy consumption
  • Longer pump and vessel lifespan
  • Fewer service calls
A properly commissioned vessel is the foundation of a reliable water pressure system. For more info contact Wates Pressure Vessel Supplier in UAE or call us at +971 4 2522966.

0 Comments

Your comment will be posted after it is approved.


Leave a Reply.

    Author

    Write something about yourself. No need to be fancy, just an overview.

    Archives

    December 2025
    July 2025
    June 2025
    October 2024

    Categories

    All

    RSS Feed

We Would Love to Have You Visit Soon!


Hours

Mon-Sat: 8am - 6pm

Telephone

+971 4 25 22 966

Email

[email protected]